1. |
Connect the GDS on the Data Link Connector (DLC).
|
2. |
Start the engine and measure the output voltage of
TPS 1 and 2 at C.T. and W.O.T.
|
1. |
Turn the ignition switch OFF.
|
2. |
Disconnect the ETC module connector.
|
3. |
Measure resistance between the ETC module terminals
1 and 2.
|
4. |
Check that the resistance is within the specification.
|
Removal and Installation
1.
Disconnect the battery negative terminal.
Tightening torque
(-) terminal :
4.0 ~ 6.0N.m (0.4 ~ 0.6kgf.m, 3.0 ~ 4.4l ...
Installation
•
Install the component with the specified
torques.
•
...
Line Pressure Control Solenoid Valve. Schematic Diagrams
Circuit Diagram
...